Rejection French-speaking chamber

Rejection of I'll Be Bag's appeal against the covid face mask framework agreement (Defense) — first challenged act (award) annulled by companion judgment 261.999 — choice of negotiated procedure without prior publication justified by covid-19 compelling urgency — no substantial modification during execution (subcontractor change and mask conformity)

Ruling nr. 262000 · 16 January 2025 · VIe kamer

The Council of State rejected the appeal of SA I'll Be Bag against the framework agreement for reusable face masks (covid-19) concluded by Defense: the first challenged act (award) having been annulled by companion judgment no. 261.999 rendered the same day, grounds 1 to 4 became moot; the fifth ground (substantial modification during execution) was rejected regarding both the alleged subcontractor change of Tweeds & Cottons (the Wall AG exception applies only exceptionally and ESQUEL invoices confirmed deliveries) and the alleged non-conformity of Avrox masks (the 60°C washing norm was a recommendation to users, not manufacturers) — the Council declared itself incompetent for this third act; the sixth ground (choice of procedure) was rejected: compelling urgency was justified (NSC 24 April 2020, GEES 22 April 2020, procurement completed in 7 days) and the framework agreement until 31 December 2020 was not manifestly unreasonable in a market disrupted by the pandemic.

What happened?

On 24 April 2020, Belgium's National Security Council, based on the GEES expert group's advice of 22 April, decided on progressive deconfinement accompanied by generalized mask-wearing. On 27 April, the Council of Ministers tasked the Defense Minister with procuring reusable face masks through a framework agreement via negotiated procedure without prior publication (Art. 42 §1(1)(b)). After market prospection with 190 textile operators in two rounds, 41 operators were invited to tender on 3 May. The specifications required a declaration attesting delivery of at least 250,000 fabric masks (qualitative selection), compliance with norm NBN/DTD S 65-001:2020 v.1.1, and a maximum unit price of EUR 2.50. Thirty offers were submitted on 4 May. On 5 May, the Minister awarded the contract to Tweeds & Cottons and Avrox and rejected I'll Be Bag's offer. I'll Be Bag filed an annulment action against three acts: (1) the award decision, (2) the choice of procedure, and (3) the implicit decision to substantially modify the framework agreement during execution. The Council ruled the same day as companion judgment no. 261.999, which annulled the award decision, rendering grounds 1-4 moot. On the fifth ground (substantial modification), the Council found: (branch 1) the Wall AG exception applies only exceptionally and ESQUEL invoices confirmed delivery by the announced subcontractor; (branch 2) the 60°C washing recommendation in the technical norm was addressed to users, not manufacturers. The Council declared itself incompetent for the third act. On the sixth ground (choice of procedure), both branches were rejected: compelling urgency was established (3-day response, 7-day procurement) and the 8-month framework agreement was not manifestly unreasonable given the disrupted market. Confidentiality of all 36 pieces (offers and comparison table) was maintained. The application was rejected, with costs charged to the State due to the companion annulment.

Why does this matter?

This ruling, rendered the same day as companion judgment no. 261.999 in the emblematic covid-19 mask procurement case, clarifies several important issues: the three cumulative conditions for compelling urgency were met (the scientific controversy over mask efficacy constituted an unforeseeable event); a framework agreement of 8 months is not incompatible with strict necessity when the market is disrupted; the Wall AG subcontractor change exception applies only when the subcontractor's identity was a determining factor; and technical norm recommendations must be interpreted according to their addressee (users vs. manufacturers).

The lesson

As a contracting authority: document all three cumulative conditions for compelling urgency carefully. A framework agreement is not excluded but its duration must remain proportionate to actual uncertainty. Specify explicitly whether a subcontractor's identity is an essential element of the contract. As a tenderer: challenge the procedure choice in a timely manner; however, participation without prior protest does not necessarily eliminate your interest if the urgency conditions caused you prejudice. To invoke a substantial modification during execution, you must concretely demonstrate how conditions became materially different.

Ask yourself

As a contracting authority: are all three conditions of Article 42 §1(1)(b) documented and cumulatively met? Is the framework agreement duration proportionate to the actual urgency? Did you act without delay after the triggering event? Are modifications during execution documented and justified under Article 38/6? As a tenderer: do you have a concrete interest in challenging the procedure choice? Are the substantial modifications you invoke supported by concrete evidence? Does the technical norm you rely on address manufacturers or users?

About this database

The Council of State (Raad van State / Conseil d'État) is Belgium's supreme administrative court. In disputes over public procurement — from contract awards to tenderer exclusions — the Council of State is the final arbiter. The rulings in this database are summarised by TenderWolf in plain language, with practical lessons for tenderers and contracting authorities. View all rulings →